Fredericton Esso – Complete Petroleum Equipment Replacement
July 2006 – August 2006
This project involved the complete replacement of all petroleum equipment including underground fiberglass tanks, underground distribution piping, tank equipment, and dispensers. This work included all earthworks, concrete, asphalt, and electrical.
![]() |
![]() |
![]() |
![]() |
Bedford Ultramar – General/Petroleum Contractor
September 2006 – October 2006
This project involved the complete replacement of all petroleum equipment including underground fiberglass tanks, distribution piping, tank equipment, and dispensers. This work included all earthworks, concrete, asphalt, and electrical.
![]() |
![]() |
![]() |
![]() |
Rockingham Ridge Wilsons – General/Petroleum Contractor
August 2004 – October 2004
This project involved an upgrade of an existing petroleum installation at a retail outlet including all distribution piping, islands, aprons, and dispensers. This work included all earthworks, concrete, asphalt, and electrical.